INSTALLATION PROCEDURE
This NAP explains the procedures for installing the power equipment.
Note: The Circuit Breaker (NFB) for the Rectifier's DC output must remain OFF.
NAP-200-006
Sheet 1/1
Installation of Power Equipment
START
Install the power equipment at the predetermined location using anchor bolts, etc. Install the framework
for the batteries to be used for backup. Secure the framework using anchor bolts, etc.
Check the cabling at the primary and secondary sides of the power equipment, and the cabling to the
batteries
Confirm that the specifications of the customer-installed AC PDB (NFB capacity, voltage, phase, etc.)
conform to the specifications of the Rectifier.
Confirm that the proper communication ground is available.
Connect the input power cable and grounding cable to the rectifier.
Supply electrolyte to each battery as per the specifications of the battery.
Charge the batteries after verifying that the rectifier is operating normally.
END
ATTENTION
Contents
Static Sensitive
Handling
Precautions Required